What a work day on Marine Way means for you
What the project documents say today. Anything the documents don’t cover yet is marked To be confirmed.
At a glance
Noise and vibration
The loudest stretch is seawall sheet piling with a vibratory hammer, planned 19 Feb 2027 to 23 Apr 2028 (main seawall piling 8 Aug 2027 to 3 Feb 2028).
Vibration and settlement next to the historic homes are monitored continuously against stop-work limits, and nearby structures get a condition survey before work starts.
Noise limits and quiet hours: To be confirmed.
Exhibit A.1 schedule, 14 Sep 2026
Trucks and deliveries
Concrete trucks and cranes at the pump station site while it is built (planned 16 Dec 2027 to 23 Apr 2029). A field office and laydown yard are set up at the start.
Truck routes and delivery times: To be confirmed.
Exhibit A.1 schedule
Road and lane closures
Traffic control is in place for most of the job (planned 31 Oct 2026 to 1 Dec 2029). The first detours and a protected walking route go in 31 Oct to 29 Nov 2026. Emergency access is kept at Deck 84.
Detour map and closure dates by block: To be confirmed.
Exhibit A.1 schedule
Parking and driveways
Driveway access is phased while the new paver street is built on North Marine Way (planned Feb to May 2029). Driveways and walkways are rebuilt in kind to match.
When finished: 8-ft grass-pave parking beside the paver street on North Marine Way.
Parking during construction: To be confirmed.
Exhibit A.1; plan sheets C5.0, C8.x
Docks and boat access
Existing docks along North Marine Way are removed and salvaged (planned Sep to Oct 2027) and rebuilt with gangways, dock utilities and fender piles (planned Sep 2028 to Jan 2029). Boat traffic close to the outfall work may be affected. Floating turbidity barriers protect the water.
Temporary slips or boat access during dock work: To be confirmed.
Exhibit A.1; plan sheet C4.0
Work hours
The contract allows Saturday, Sunday, holiday and after-hours work only if the City approves it.
Normal weekday work hours: To be confirmed.
Agreement §13.8
Water and sewer service
Short planned water and sewer interruptions during tie-ins, with sewer bypass pumping (main utility work planned Jul to Dec 2028). Advance notice before any shut-off.
Exhibit A.1 schedule
Sources: Exhibit A.1 Accepted GMP Schedule (CPM), 14 September 2026, traditional vibratory basis (proposed until the City executes the GMP amendment); Construction Manager at Risk Agreement, City of Delray Beach and Man-Con, Inc. (Resolution 69-26); plan sheets C4.0, C5.0 and C8.0–C8.4, Project 17-047, prepared by WGI. Phase map · Before and after